TRANSMISSION & DISTRIBUTION

Moca GIS

Location: Moca, PR
Client: PREPA 
Completion Date: 2010
Project Description:

This bid was awarded to RG Engineering (RGE).This project consists of the design, supply, installation and construction of a new 38 kV GIS. RGE contracted MEC to prepare the complete Electrical design of this important project, which included the coordination with PREPA during commissioning.

 

7

AMGEN GIS

Location: Juncos, PR
Client: AMGEN
Completion Date: 2008
Project Description:

Design, supply, installation supervision and commissioning . This project consists of a substation of 38 KV and 115 (18 switches) using GIS technology Siemens and Alstom . It also has a system of protection and control all networked with the Puerto Rico Electric Power Authority.

 

amgen

Banco Popular GIS

Location: San Juan, PR
Client: Banco Popular de Puerto Rico
Completion Date: 2010
Project Description:

Design, supply , supervision , commissioning and construction of a substation of 38 KV ( 4 switches ) Siemens using GIS technology. It has a of protection system and is connected to the network of the Electric Power Authority control.

 

bp

Coliseo de Puerto Rico GIS

Location: San Juan, PR
Client: Coliseo de Puerto Rico
Completion Date: ?
Project Description:

Design, supply , supervision , commissioning and construction of a substation of 38 KV ( 5-bay ) using GIS technology from Siemens . It has a protection system and is connected to the network of the Electric Power Authority control.

 

cp

Mall of San Juan GIS

Location: San Juan, PR
Client: Mall of San Juan
Completion Date: 2010
Project Description:

A substation of 38 KV GIS using Siemens technology was designed, managed and built. It has a protection system connected to the network and ESA control.

 

34 copy

Static Bar Compensator 

Location: Bayamon, PR
Client: AEE
Completion Date: 2010
Project Description:

Design, supply , supervision, commissioning and installation of static compensator reactive load. It has a protection system and connected to the network of the Electric Power Authority control.

 

stb

Buchanan

Location: Guaynabo, PR
Client: US Corps of Engineers
Completion Date: 2010
Project Description:

Design of a 38 KV substation with two 20 MVA transformers in parallel, and replacement of three airlines of 13.2 KV to serve a military base in Puerto Rico. It has a protection system connected to the network and ESA control.

 

b

LAESA Pimentel I & II

Location: Pimentel, Dominican Republic
Client: LAESA, Ltd
Completion Date: 2010
Project Description:

An extension to the existing substation of 138 KV conventional type was designed, managed and built to provide interconnection to the network of the Dominican Republic. It has ___ MVA transformer , a protection and control system which is connected to the system of the Dominican Republic.

 

p1y2

LAESA Pimentel III

Location: Pimentel, Dominican Republic
Client: LAESA, Ltd
Completion Date: 2010
Project Description:

An extension to the existing substation of 138 KV conventional type was designed, managed and built to provide interconnection to the network of the Dominican Republic. It has ___ MVA transformer , a protection and control system which is connected to the system of the Dominican Republic.

 

p3